Acres International - Innovations (Summer 2004)
  El Canadá hydroelectric facility on the Río Samalá in GuatemalaAcres drives financial and environmental success on the Rio Samalá  
     
 

The Río Samalá is situated in a spectacular mountainous area in the southwest region of Guatemala, 100 km west of Guatemala City. The river flows south to the Pacific Ocean through steep, lush terrain dominated by several active volcanoes. The identified development site was immediately downstream from an existing power plant and bordered the El Canadá farm. Acres established a development partnership with the local farm owner and began planning activities in September 1998.

A team of Acres engineers, led by Robert Eggink and Ian Ainslie, propelled the project’s startup with a site walkover and preinvestment brochure including conceptual drawings, energy estimates and construction cost estimates. This was used to define project features and economic attractiveness to potential investors. Subsequently, ENEL North America agreed to invest in the project and contracted Acres as lead engineer and Owner’s Engineer during construction. The original Acres team continued work and saw the El Canadá project through to successful completion.

For the initial feasibility study, subsurface investigations and topographic surveys were undertaken to assess the optimum configuration for El Canadá. The configuration recommended by Acres included a small rubber diversion dam, flushing structure, desander, 1.2-km tunnel, 5-hour peaking reservoir, penstock intake structure, 2.4-km buried steel penstock, 43-MW 2-Pelton unit powerhouse, substation, transmission line and several kilometers of access road. The plant has a gross head of 395 m.

 
 
 

 


Acres produced a tender-level design, complete with water-to-wire specifications, drawings and civil works specifications. Contracts with the developer were awarded to the successful EPC contractor and water-to-wire contractor. Acres reviewed final design and provided site representation to ensure compliance with contract documents.

By successfully promoting this hydro development, Acres was able to prevent the future possibility of thermal plant construction and avoid associated emissions. In addition to design-specific environmental considerations, the plant’s construction had a number of beneficial side-effects including sub-surface water conservation, river cleansing and reforestation. For example, the trash-handling system designed to prevent debris from entering El Canadá’s turbines simultaneously acts as a much-needed system to remove garbage from the Río Samalá.

     
 

With these positive effects taken into consideration, as well as El Canadá’s contribution to greenhouse gas reductions in accordance with the Kyoto Protocol, ENEL Latin America was successful in receiving carbon credits from the World Bank Prototype Carbon Fund. ENEL’s commitment to the project also went beyond plant confines to include substantial infrastructure investments to improve the conditions of the neighboring communities.

The El Canadá plant started producing energy ahead of schedule, near the end of 2003, and is one of the first renewable energy projects to be developed after the approval of Guatemala’s new General Electricity Law. El Canadá also acts as a development model, providing invaluable knowledge and experience for other parties interested in entering this challenging market.

 
 

For further information, please contact:

 

 
 
   Ian Ainslie
Acres International, Niagara Falls, ON
905-374-5200
iainslie@acres.com

 

 
 
   Robert Eggink
Acres International, Amherst, NY
716-689-3737
reggink@acres.com

 

 
 

« Back to the newsletter listings