HydroVantage Establishes Spare Part Strategy at Beauharnois Power Plant

Hydro-Québec's Beauharnois Plant contains 36 generating units, each equipped with a single 3-phase transformer. Failure of a transformer would result in a loss of CAN$30,000 each day that its associated unit is out of commission. In order to develop the most effective strategy for dealing with potential transformer failures, Hydro-Québec performed a risk-based analysis using HydroVantage, Synexus Global's web-based decision support software for capital investment planning.

Hydro-Québec was able to construct a detailed model which considered the individual characteristics of each of the 36 transformers, and also an aggregate model for a bank of standard transformers. Sensitivity analyses were conducted and correlated between the two models. The resulting recommendation was immediate purchase of a single spare transformer, which would create a significant saving in case of a failure. Purchase of a second spare at a future date is also justified, while a third spare cannot be justified at any time.

"HydroVantage recommended the right amount of investment at the right time to avoid significant production losses in case of major failures. Recommendations have been fully implemented." Bernard Bourgeois, Assistant Plant Manager, Beauharnois Power Plant.

Download detailed project description